Key facts
- WhenTrack lien-risk status before annual holdback release, final holdback release, and closeout payment events.
- Form or ruleLien preservation and holdback risk tracking
- Who enforces itOntario Ministry of the Attorney General / Construction Act framework
- If it is missedUntracked lien risk can block holdback release and create owner, GC, and subcontractor payment exposure.
- LawConstruction Act, R.S.O. 1990, c. C.30
Who does this apply to?
This compliance requirement applies to all owners, general contractors, subcontractors, and trades operating within the Ontario construction sector. Any entity executing construction contracts, administering payments, or managing holdbacks must track lien-risk status. This tracking is mandatory before executing annual holdback releases, final holdback releases, and project closeout payment events. The scope is determined by contract duration and structure rather than specific worker counts or equipment classes; any contract extending beyond one year triggers mandatory annual holdback tracking.
What are the deadlines?
- Mandatory Annual Holdback Publication: For contracts extending beyond one year, owners must publish a Notice of Annual Release of Holdback (Form 6) on an electronic construction trade news website within 14 days after each contract anniversary.
- Holdback Payment Window: Accrued basic holdback must be paid to the contractor no earlier than day 60 and no later than day 74 after the publication of Form 6, provided no liens have been preserved.
What happens if it is missed?
Failing to track lien risk or mismanaging payment timelines exposes payers to significant financial liability under the Construction Act payment administration framework. Untracked lien risk can block holdback releases and create severe payment exposure across the entire construction pyramid.
- Repeal of Section 27.1: Payers can no longer publish a notice of non-payment to refuse holdback distribution due to deficient or incomplete work. Holdback usage is strictly limited to formal contract abandonment or termination scenarios and preserved lien risk.
How do you do it, step by step?
- Step 1: Invoice Intake Audit: Upon receipt of any invoice, immediately review its structure. If any deficiency is found, draft and deliver a formal written notice of deficiency within 7 days.
- Step 2: Track Contract Anniversaries: For projects extending beyond 12 months, log the exact contract anniversary date to trigger the annual holdback release process.
- Step 3: Publish Form 6: Prepare and publish the Notice of Annual Release of Holdback (Form 6) on an electronic construction trade news website within 14 days after the contract anniversary.
- Step 4: Monitor Lien Registry: Monitor the land registry for any preserved liens during the 60-day period following the publication of Form 6.
- Step 5: Release Holdback: If no liens are preserved, release the accrued basic holdback between day 60 and day 74 post-publication.
- Step 6: Initiate Adjudication if Disputed: If a payment dispute arises, file a notice of adjudication with ODACC within 90 days of contract completion, abandonment, or termination.
Official sources
Every fact on this page traces back to a primary Government of Ontario source. Verify against the original before relying on it.
- Filing and guidance pageontario.ca
- Ontario e-Laws: regulation textontario.ca