What does the Holdback Release Package record?
- Contract and holdback amount
- Release trigger: substantial performance, completion or annual release
- Lien period end date and lien search result
- Statutory declarations and WSIB clearance
- Holdback invoice
- Subtrade holdback to pass down
Which Ontario rule applies?
Under the Construction Act each payer retains a 10 percent basic holdback (s. 22) and releases it once the lien period passes with no liens preserved. The linked rule pages cover annual release and the payment window.
Read the law
The rule step by step
Key facts
- Used byGeneral Contractors, Subcontractors & Project Administrators
- FormatChecklist of 6 items to complete and keep with the project file