Form 6 Annual Holdback Release

On an Ontario contract that runs longer than a year, the owner must publish a notice of annual release of holdback in the prescribed form no later than 14 days after each anniversary, stating the holdback it intends to pay and the payment date (Construction Act, section 26). The accrued holdback is then paid at least 60 and no later than 74 days after publication, unless a lien has been preserved or perfected.

Published by Blue Crane Works. Last reviewed . Drafted with AI assistance from the official sources listed below; the answer above was checked against Ontario's e-Laws by the publisher.

Get Form 6

Form 6 is published by Ontario Ministry of the Attorney General / Construction Act framework. These links go to the government’s own copy, so you always get the current version.

Key facts

  • WhenFor contracts extending beyond one year, publish Form 6 within 14 days after each contract anniversary.
  • Form or ruleNotice of Annual Release of Holdback (Form 6)
  • Who enforces itOntario Ministry of the Attorney General / Construction Act framework
  • If it is missedFailure to publish or track Form 6 can disrupt statutory holdback release and lien-risk administration.
  • LawConstruction Act, R.S.O. 1990, c. C.30
  • LawO. Reg. 304/18

Who does this apply to?

This compliance requirement applies to owners, general contractors, and subcontractors executing construction contracts in Ontario that extend beyond one year. It is mandatory for projects where the contract explicitly provides for the annual release of holdback. The scope covers all trades, project values, and licence categories operating under such multi-year contract structures.

What are the deadlines?

  • Form 6 Publication Window: For contracts extending beyond one year, owners must publish Form 6 on an electronic construction trade news website within 14 days after each contract anniversary.
  • Holdback Payment Window: Accrued basic holdback must be paid to the contractor between day 60 and day 74 after the publication of Form 6, provided no liens have been preserved.

What happens if it is missed?

  • Non-Compliance Penalty: Failure to publish or track Form 6 can disrupt statutory holdback release and lien-risk administration. No verified statutory fine amount is specified in the source data; liability is limited to Construction Act payment administration exposure and potential breach of contract or lien claims.

How do you do it, step by step?

  • Step 1: Track Contract Anniversaries: Monitor project schedules to identify contracts extending beyond one year that permit annual holdback release.
  • Step 2: Prepare Form 6: Complete the Notice of Annual Release of Holdback (Form 6) in accordance with O. Reg. 304/18.
  • Step 3: Publish Form 6: Upload and publish the completed form on an electronic construction trade news website within 14 days after the contract anniversary.
  • Step 4: Monitor Lien Registry: Verify that no liens have been preserved against the premises or contract during the statutory period.
  • Step 5: Execute Payment: Release and pay the accrued basic holdback between day 60 and day 74 following the publication date.
  • Step 6: Document Compliance: Retain the publication certificate, payment records, and any related proper invoices in the project compliance file.