Notice of Non-Payment Prompt Payment Control

A notice of non-payment is how a payer under Ontario's Construction Act refuses to pay all or part of a proper invoice. An owner must give it in the prescribed form within 14 days of receiving the invoice, stating the amount not being paid and why. A contractor that is not paid can pass the dispute down to its subcontractors with its own notice, undertaking to refer the matter to adjudication.

Published by Blue Crane Works. Last reviewed . Drafted with AI assistance from the official sources listed below; the answer above was checked against Ontario's e-Laws by the publisher.

Get Form 1.2

Form 1.2 is published by Ontario Ministry of the Attorney General / Construction Act framework. These links go to the government’s own copy, so you always get the current version.

Key facts

  • WhenTrack notice of non-payment steps and downstream communication windows when a payer disputes payment after receiving an invoice.
  • Form or rulePrompt payment notice response
  • Who enforces itOntario Ministry of the Attorney General / Construction Act framework
  • If it is missedLate or incomplete notice administration can shift payment liability and escalate to adjudication.
  • LawConstruction Act, R.S.O. 1990, c. C.30

Who does this apply to?

This compliance control applies to all construction contracts in Ontario governed by the Construction Act, R.S.O. 1990, c. C.30. It mandates strict administrative protocols for owners, general contractors, subcontractors, and trades across all project values, worker counts, and licence categories. Any payer who disputes a proper invoice, or any contractor who receives a notice of non-payment and must pass that notice downstream to subcontractors, must track and execute these communication windows.

What are the deadlines?

  • 7-Day Invoicing Rule: Invoices are legally deemed proper unless the owner gives a formal written notice of deficiency within 7 days after receiving the invoice. Missing this 7-day notice window forfeits the right to dispute invoice form or structure and starts the 28-day prompt-payment timeline.
  • Adjudication Extension: Parties have a strict 90-day window after contract completion, abandonment, or termination to initiate interim binding adjudication through ODACC or a qualified private adjudicator.

What happens if it is missed?

  • Non-Compliance Penalty: Late or incomplete notice administration can shift payment liability and escalate to adjudication. There is no verified statutory dollar amount specified in the source data for administrative non-compliance penalties; however, failing to issue notices within the mandated windows legally obligates the payer to pay the full invoiced amount.

How do you do it, step by step?

  • Step 1: Invoice Intake and Review: Upon receipt of an invoice, immediately review its structure. If any deficiencies exist, draft and deliver a formal written notice of deficiency to the contractor within 7 days of receipt.
  • Step 2: Notice of Non-Payment Issuance: If disputing payment of a proper invoice, the owner must deliver a Notice of Non-Payment to the contractor within 14 days of receiving the proper invoice, detailing the amount disputed and the reasons for non-payment.
  • Step 3: Downstream Notification: If a contractor receives a Notice of Non-Payment from an owner, they must refer to the downstream communication windows and issue their own Notice of Non-Payment to affected subcontractors within 7 days of receiving the owner's notice.
  • Step 4: Holdback Administration: For multi-year contracts, track the contract anniversary. Publish Form 6 (Notice of Annual Release of Holdback) on an electronic construction trade news website within 14 days after the anniversary. Release the accrued basic holdback between day 60 and day 74, ensuring no liens are preserved. Do not attempt to use the repealed Section 27.1 mechanism to refuse holdback distribution for deficient work.
  • Step 5: Dispute Resolution: If a payment dispute cannot be resolved, initiate interim binding adjudication through ODACC or a qualified private adjudicator within the strict 90-day window following contract completion, abandonment, or termination.

Official sources

Every fact on this page traces back to a primary Government of Ontario source. Verify against the original before relying on it.

Plain-Language Explainer

The Form 1.2 21-day window explained, and what missing it costs · on Blue Crane Works, the publisher of this registry.