Key facts
- WhenTrack the 90-day post-completion, abandonment, or termination adjudication window for eligible disputes.
- Form or ruleInterim binding adjudication timing
- Who enforces itOntario Dispute Adjudication for Construction Contracts
- If it is missedMissed adjudication windows can remove a fast interim dispute-resolution path and force slower escalation.
- LawConstruction Act, R.S.O. 1990, c. C.30
Who does this apply to?
This requirement applies to all parties operating under a construction contract in Ontario, including owners, general contractors, subcontractors, and trade contractors. Regardless of worker counts, project values, or specific trade licence categories, any party seeking to resolve a payment or contract dispute through the interim binding adjudication process must adhere to this timeline. Eligible disputes include those concerning proper invoices, payment certificates, holdbacks, or the valuation of services and materials.
What are the deadlines?
Compliance officers must align project closeout and dispute tracking with the following strict statutory timelines:
- Adjudication Window: Parties have a strict 90-day window after contract completion, abandonment, or termination to initiate interim binding adjudication through ODACC or a qualified private adjudicator.
What happens if it is missed?
Failing to initiate adjudication within the mandatory timeframe carries significant operational and financial risks:
- Loss of Interim Remedy: Missing the 90-day adjudication window removes the fast, interim binding dispute-resolution path, forcing parties to escalate disputes through slower and more expensive court litigation or formal arbitration.
How do you do it, step by step?
- Step 1: Track Project Status: Document and verify the exact date of contract completion, abandonment, or termination to establish the start of the 90-day adjudication window.
- Step 2: Access the ODACC Portal: Log into the electronic registry at https://odacc.ca/ to initiate the dispute process.
- Step 3: Draft the Notice of Adjudication: Complete the electronic form specifying the nature of the dispute, the contract details, the amount in dispute, and the proposed adjudicator.
- Step 4: Serve the Notice: Submit the notice through the ODACC system and serve it on the responding party within the contractually or statutorily required timelines.
- Step 5: Maintain Project Records: Retain copies of all proper invoices, 7-day deficiency notices, Form 6 publications, and proof of service within the corporate compliance file.
Official sources
Every fact on this page traces back to a primary Government of Ontario source. Verify against the original before relying on it.
- Filing and guidance pageodacc.ca
- Ontario e-Laws: statute textontario.ca