Key facts
- WhenTrack the 28-day owner payment timeline from receipt of a proper invoice unless the Act permits a valid notice response.
- Form or ruleConstruction Act prompt payment timeline
- Who enforces itOntario Ministry of the Attorney General / Construction Act framework
- If it is missedFailure to track the payment window can create payment disputes, adjudication exposure, and downstream subcontractor cash-flow pressure.
- LawConstruction Act, R.S.O. 1990, c. C.30
Who does this apply to?
This requirement applies universally to all construction contracts and subcontracts executed within the province of Ontario. It governs all trade categories, general contractors, and subcontractors across all tiers, regardless of project value, worker counts, or equipment classes. Any entity issuing or receiving an invoice for construction services or materials must adhere strictly to these statutory timelines.
What are the deadlines?
- 7-Day Invoicing Rule: Invoices are legally deemed proper unless the owner delivers a formal written notice of deficiency to the contractor within 7 days of receipt. Missing this 7-day window forfeits the owner's right to dispute the invoice layout or structure and immediately triggers the 28-day prompt-payment timeline.
- 28-Day Payment Timeline: The owner must pay the contractor within 28 days of receiving a proper invoice, unless a formal notice of non-payment is given within the permitted statutory timelines.
What happens if it is missed?
- Non-Compliance Penalty: Failure to track the payment window can create payment disputes, adjudication exposure, and downstream subcontractor cash-flow pressure. No verified statutory fine amount is specified in the source data, but non-compliance triggers interest penalties and immediate adjudication risk.
How do you do it, step by step?
- Step 1: Submit Proper Invoice: The contractor must submit a "proper invoice" to the owner. Ensure it meets all statutory requirements of the Construction Act.
- Step 2: Monitor the 7-Day Dispute Window: Track the 7-day period from invoice receipt. If no formal written notice of deficiency is received from the owner within 7 days, the invoice is legally deemed proper.
- Step 3: Track the 28-Day Payment Deadline: Ensure payment is received or issued within 28 days of the proper invoice receipt.
- Step 4: Manage Holdbacks (Form 6): For multi-year contracts, publish the Notice of Annual Release of Holdback (Form 6) on an electronic construction trade news website within 14 days of the contract anniversary. Pay the accrued basic holdback between day 60 and day 74 post-publication, provided no liens are preserved.
- Step 5: Initiate Adjudication if Required: If a payment dispute arises, initiate interim binding adjudication through ODACC or a qualified private adjudicator within the strict 90-day window following contract completion, abandonment, or termination.
Official sources
Every fact on this page traces back to a primary Government of Ontario source. Verify against the original before relying on it.
- Filing and guidance pageontario.ca
- Ontario e-Laws: regulation textontario.ca
Plain-Language Explainer
The prompt-payment clock explained, deadline by deadline · on Blue Crane Works, the publisher of this registry.