What does the Notice of Project (NOP) record?
Collects everything the Ministry's Notice of Project filing asks for, then records the confirmation number and keeps the on-site copy.
| Field | Required | Answer type |
|---|---|---|
| Constructor Operating / Trade Name | Yes | Short answer |
| Company Official (First and Last Name) | Yes | Short answer |
| Position or Title | Yes | Short answer |
| Constructor Head Office Address | Yes | Notes |
| Telephone Number | Yes | Short answer |
| Project Address (or lot, plan, nearest intersection) | Yes | Notes |
| Town / City / Township | Yes | Short answer |
| Project Description | Yes | Notes |
| Expected Start Date | Yes | Date |
| Expected Completion Date | No | Date |
| Expected Cost of Labour and Materials | Yes | Number |
| Date Filed with the Ministry | No | Date |
| eNOP Confirmation / Reference Number | No | Short answer |
| Notes | No | Notes |
Which Ontario rule applies?
Preparation worksheet and on-site record for a Notice of Project under O. Reg. 213/91 (Construction Projects), s. 6. An NOP is required before work begins where the expected cost of labour and materials exceeds $50,000 — $250,000 at an automotive manufacturing or assembly facility — and for certain high-hazard work at any value. Filing itself is done on the Ministry's eNOP portal; this worksheet does not submit anything.
Read the law
The rule step by step
Key facts
- Used byGeneral Contractors, Project Managers & Contract Administrators
- Also callednop, notice of project, o. reg. 213/91, form 0175, ministry of labour notice
- Format14 fields to fill in, then sign and keep with the project file