What does the Pre-Construction Meeting Agenda record?
- Introductions, roles and contacts
- Scope, schedule and milestones
- Constructor named; registration (Form 1000) and Notice of Project
- Site-specific safety plan and emergency procedures
- Site logistics: access, hours, parking and storage
- Submittals, RFIs, change orders and the payment process
- Minutes and action items
Which Ontario rule applies?
Under O. Reg. 213/91 every constructor and employer must complete a registration before beginning work at a project (s. 5), and a Notice of Project is required before work begins where the expected cost of labour and materials exceeds $50,000 (s. 6). The constructor must also establish written emergency procedures for the project (s. 17).
Read the law
The rule step by step
Key facts
- Used byGeneral Contractors & Owners
- FormatChecklist of 7 items to complete and keep with the project file