Key facts
- Work it coversElectrical / welding and cutting work
- WhenBefore each welding, cutting, blow-torch, or similar ignition-source task where the constructor or employer uses a hot-work permit control.
- RuleO. Reg. 213/91, ss. 122-124, Welding and Cutting; s. 123 requires precautions to prevent fire when using a blow torch, welding or cutting equipment, or similar equipment.
- Who signsHot-work permit issuer, competent worker performing the work, and fire-watch or supervisor acknowledgement where the project hot-work procedure assigns those roles.
- Keep itRetain with the project safety file according to the constructor's hot-work procedure and contract recordkeeping requirements.
When must the log be completed?
- Required Timing: Before each welding, cutting, blow-torch, or similar ignition-source task where the constructor or employer uses a hot-work permit control.
- Supervisor Review: Assign a competent person or supervisor to review the entry before the next shift or before the controlled work resumes.
- Change Trigger: Re-open the log when weather, equipment, excavation, access, crew, or work-method conditions change.
How do you complete the log?
- Identify the Controlled Work: Record the site, date, crew, equipment, area, and trade activity.
- Check the Hazard Controls: Confirm guards, access, PPE, training, permits, isolation, or inspection evidence required for the task.
- Sign the Entry: Hot-work permit issuer, competent worker performing the work, and fire-watch or supervisor acknowledgement where the project hot-work procedure assigns those roles.
- Store the Record: Retain with the project safety file according to the constructor's hot-work procedure and contract recordkeeping requirements.
Official sources
Every fact on this page traces back to a primary Government of Ontario source. Verify against the original before relying on it.
- Ontario e-Laws: regulation textontario.ca
- CanLII: consolidated textcanlii.org