Ontario contractor template

Hot Work Permit Template

A hot work permit is the sign-off completed before welding, cutting, grinding or torch work: the area checked, combustibles removed or covered, an extinguisher in place and a fire watch assigned. In Ontario, O. Reg. 213/91 requires precautions against fire whenever blow torches, welding or cutting equipment are used.

Published by Blue Crane Works. Last reviewed . Field list from the Blue Crane Works form library. Summary drafted with AI assistance; every rule cited was checked against Ontario's e-Laws.

What does the Hot Work Permit record?

Permit for welding, cutting, grinding, fire watch, and area readiness checks.

Hot Work Authorization Permit: 11 fields, 10 required
FieldRequiredAnswer type
Company NameYesShort answer
Project / Site NameYesShort answer
Hot Work LocationYesShort answer
Permit DateYesDate
Start TimeYesTime
End TimeYesTime
Permit Issued ByYesShort answer
Fire Watch Assigned ToYesShort answer
Precautions / Area ChecksYesNotes
Combustibles / ControlsYesNotes
Final Fire Watch / Completion NotesNoNotes

Which Ontario rule applies?

O. Reg. 213/91 (Construction Projects), ss. 122–124, Welding and Cutting. Section 123 requires precautions against fire when using a blow torch, welding or cutting equipment.

Read the law

Key facts

  • Used byWelding, Roofing & Mechanical Contractors
  • Also calledwelding permit, cutting permit, hot work permit
  • Format11 fields to fill in, then sign and keep with the project file