Change-Order Documentation Compliance

Change order documentation is the written record that changed work was requested, priced and approved before it was billed. Ontario's Construction Act does not prescribe a change order form, but a proper invoice must identify the authority under which the work was supplied (section 6.1), and disputes over payment for changed work can go to adjudication. Undocumented changes are the hardest work to get paid for.

Published by Blue Crane Works. Last reviewed . Drafted with AI assistance from the official sources listed below; the answer above was checked against Ontario's e-Laws by the publisher.

Key facts

  • WhenDocument changed work before billing, including directive date, backup, approval authority, and invoice connection.
  • Form or ruleConstruction contract change documentation
  • Who enforces itOntario Construction Act & CCDC contract administration
  • If it is missedPoor change-order records increase invoice deficiency disputes and payment-delay exposure.
  • LawConstruction Act, R.S.O. 1990, c. C.30

Who does this apply to?

This compliance requirement applies to all construction trades, general contractors, subcontractors, and project owners operating within Ontario's construction sector. Any change to the original contract scope-regardless of project value, worker count, or trade category-must be formally documented. This includes capturing the directive date, detailed backup documentation, approval authority signatures, and direct invoice connections before any changed work is billed.

What are the deadlines?

  • Pre-Billing Documentation: All changed work must be fully documented and approved before it is included in any billing cycle.
  • 7-Day Invoicing Rule: Invoices containing change-order amounts are legally deemed proper unless the owner delivers a formal written notice of deficiency within 7 days of receipt. Missing this 7-day window forfeits the owner's right to dispute the invoice layout or structure and immediately triggers the 28-day prompt-payment timeline.
  • Adjudication Extension: Parties have a strict 90-day window after contract completion, abandonment, or termination to initiate interim binding adjudication through ODACC or a qualified private adjudicator to resolve change-order disputes.

What happens if it is missed?

  • Non-Compliance Penalty: There is no verified statutory fine amount prescribed for change-order documentation omissions. However, poor change-order records directly increase invoice deficiency disputes and payment-delay exposure under the Construction Act.

How do you do it, step by step?

  • Step 1: Initiate the Change Directive: Document the change immediately upon identification. Record the directive date, specific scope modifications, and the authorizing party.
  • Step 2: Gather Backup Documentation: Compile all labour hours, material receipts, and equipment rates associated with the change.
  • Step 3: Secure Written Approval: Obtain formal sign-off from the owner or authorized consultant before executing or billing the work.
  • Step 4: Link to Proper Invoice: Reference the approved change-order number directly on the proper invoice to prevent 7-day deficiency disputes.
  • Step 5: Monitor Holdback and Adjudication Timelines: Track contract anniversaries for Form 6 publication and observe the 90-day post-completion window for ODACC adjudication if payment disputes arise.