What does the Commercial HVAC Scope of Work (SOW) record?
- Equipment schedule: units, capacities and who supplies them
- Ductwork, piping and controls included and excluded
- Interfaces with electrical, plumbing and the general contractor
- Start-up, testing, balancing and commissioning duties
- Owner training, manuals and warranty terms
- Exclusions and allowances
- Sign-off by the owner or general contractor and the contractor
Which Ontario rule applies?
No Ontario law prescribes a scope-of-work form. Scope matters legally because the Construction Act's payment rules run from the contract: a proper invoice bills work under it, and changed work needs a change order. The installation itself must meet the Ontario Building Code, where Part 6 covers heating, ventilating and air-conditioning.