What does the Commercial Electrical Scope of Work (SOW) record?
- Service, distribution, lighting, power and low-voltage work included
- Equipment and fixtures supplied by the contractor versus the owner
- ESA notification of work and inspection milestones
- Utility coordination and disconnection boundaries
- Temporary power during construction
- Testing, labelling and as-built drawings
- Exclusions and sign-off
Which Ontario rule applies?
Electrical work must meet the Ontario Electrical Safety Code (O. Reg. 164/99), which requires the work to be filed with the Electrical Safety Authority and inspected. Payment for the work runs under the Construction Act's prompt-payment rules, so a clear scope is the baseline for invoices and change orders.
Read the law
Key facts
- Used byElectrical Contractors
- FormatChecklist of 7 items to complete and keep with the project file