What does the Electrical Change-Order record?
- Change number, date and who requested it
- Description of the changed work and drawings affected
- Price: labour, material and markup, or time and material
- Schedule impact in days
- ESA notification or inspection effect
- Approval signatures before work starts
Which Ontario rule applies?
The Construction Act's payment rules run from the contract, so written, approved changes are what let changed work be billed on a proper invoice and, if disputed, taken to adjudication. Electrical work, changed or not, must still meet the Ontario Electrical Safety Code.
Read the law
The rule step by step
Key facts
- Used byElectrical Contractors
- FormatChecklist of 6 items to complete and keep with the project file