What does the Site Instruction Log record?

  • Instruction number, date and time
  • Given by and received by
  • What was instructed, with location
  • Cost or time impact claimed
  • Converted to a change order, or no change
  • Acknowledgement signatures

Which Ontario rule applies?

No statute prescribes a site instruction log. Under the Construction Act payment flows from the contract, so a written record of changed instructions is what supports billing them. CCDC contracts, a private standard rather than law, separate supplemental instructions, which change neither price nor time, from change orders.

Read the law

The rule step by step

Key facts

  • Used byProject Managers & Superintendents
  • FormatChecklist of 6 items to complete and keep with the project file