What does the Subcontractor Invoice Review Checklist record?
- Date received, stamped the same day
- Proper invoice: the contents the Construction Act requires
- Quantities and percent complete against the schedule of values
- Approved change orders only
- Holdback withheld correctly
- WSIB clearance current
- Approve, or prepare a notice of non-payment in time
Which Ontario rule applies?
The Construction Act sets out what makes a proper invoice and the deadlines that follow it, and a contractor that will not pay a subcontractor in full must give a notice of non-payment in the prescribed form within the Act's deadline. Each step is on the linked rule pages.
Read the law
- Construction Act, R.S.O. 1990, c. C.30
- O. Reg. 304/18: General (under the Construction Act)
- Workplace Safety and Insurance Act, 1997
The rule step by step
Key facts
- Used byGeneral Contractors & Project Administrators
- FormatChecklist of 7 items to complete and keep with the project file