What does the Owner Directive record?
- Directive number and date
- Description of the changed work
- Basis for valuing it: unit prices, time and material, or to be agreed
- Schedule effect claimed
- Owner signature authorizing the work
- Later conversion to a change order
Which Ontario rule applies?
Owner directives are a contract mechanism (CCDC contracts call them change directives), and no statute prescribes the form. Adjudication under the Construction Act can decide disputes about the valuation of changed work, which is why the directive and the cost records behind it matter.